[Draft] Initial Environmental and social impact assessment: Iron exploitation project of Hoang Anh Ratanakiri Co., LTD
Published by: Open Development Cambodia
Data Resources (10)
Data Resource Preview - Table of content
Additional Info
Field | Value |
---|---|
Geographic area (spatial range) |
|
Topics |
|
Document type | Environmental Impact Assessment |
Contracting Parties |
|
Government Entity (multiple) |
|
Disclosure Mode | Released by local non-governmental organizations (LNGOs) |
License | CC-BY-SA-4.0 |
Copyright | Yes |
Access and use constraints |
By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use. |
Version / Edition | 1 |
Language of document |
|
Province(s) |
|
Metadata Reference Information |
Metadata last updated on 2018-08-03. For inquiries contact: Open Development Cambodia, Email: contact@opendevcam.net, Website: http://www.opendevcam.net Address: 43 St. 208, Phnom Penh, Cambodia. |
Contact |
CES Company |
Notes |
The project will utilize a total investment of US $ 26,672,451, of which the total investment budget is US $ 14,536,607 and operating capital of US $ 12,135,844 . Revenues from sales of these mineral products totaled US $ 47,384,450 in 2011, and product sales from 2012-2018 to US $ 50,000,000. |
Granted area | 260.0 |
Contract term | 9.5 |
Contract term unit | Years |
Party's obligation in the implementation of the project |
The plan for the development of the land area in the project site is divided into 260 hectares of mining area (12 zones), construction area of 30 ha, office space and other constructions, surface area system of roads 18 m long, 8 m wide, 14,40 ha, and bore forest (100m along the O-shore) has 400 ha. |
Job creation summary |
The project will help create jobs for Cambodian people, especially local people (among 181 labors) and improve training programs for these people to be able to work (can also receive overseas training). |
Number of created jobs | 181.0 |
Environmental protection obligation |
Environmental development plan, the project owner will prepare and set out some key measures to prevent and mitigate any negative environmental impacts caused by the action at any stage before operation of the project, executing the project and completing the project to ensure management The environmental resources of the area are efficient in accordance with the techniques and techniques Department of Environment. The Ministry of Environment, in cooperation with relevant institutions, will conduct monitoring, examining and compliance with environmental management plans and verify the results of the company's environmental management plan implementation. |
Environmental fund summary |
The company has developed a local community development plan (rehabilitation of forest, raising livestock and fish, repairing roads, providing technical services for planting rubber, cassava, and providing consultation service for other crops). These social funds will cost 892,000 USD in over 10 years, and budget for environmental rehabilitation is $ 189,794 USD/year. |
Related Project | |
Legacy reference document | Draft_EIA_HAR__00.07.2011.pdf |
Keywords | iron extraction,expoitation |
Open Contracting Identifier | ocds-miumsd-82eaf3d8-010e-45f2-9bea-3bf1a3a6ac1a |
Date uploaded | December 30, 2018, 05:15 (UTC) |
Date modified | October 5, 2022, 08:04 (UTC) |