Skip to content

Additional Information

Field Value
Last updated 2021၊ 4 အောက်တိုဘာ
Created 2019၊ 10 ဧပြီ
ပုံစံ PDF
လိုင်စင် unspecified
အမည် Chapter 4: Baseline environment
Resource's languages
  • အင်္ဂလိပ်ဘာသာစကား
ဖော်ပြချက်

The project will have an installed capacity of 400 MW to supply electricity to the surrounding provinces as well as for export to Vietnam. The project is Build Operate and Transfer (BOT) type and the investment cost is USD 816.23 million. The main dam length is 8km with crest 83m above the sea level and about 40m above the river. There are 5 turbine units with a capacity of 80MW each.